Road Network Development Project I ( Bala Murghab to Leman) :  Afghani., Is Rep. of :Go to Project Summary

Road Network Development Project I ( Bala Murghab to Leman) :  Afghani., Is Rep. of

Timetable


TA Name Road Network Development Project I ( Bala Murghab to Leman)
Country Afghani., Is Rep. of
TA Number 0081
Project Number 40333- 02
Fund Source/Amount[Approved]
Asian Development Fund US$176.00  million
Thematic Classification
Economic growth
Description The Project will help: (i) complete the improvements to the ring road by constructing a 143 km section from Leman to Bala Murghab; (ii) initiate the organizational restructuring and business process reengineering of MPW; (iii) produce annual investment plans and programs; and (iv) formalize contractor and consultant registration and evaluation.
Linkage to Country/Regional Strategy This is part of ADB's road infrastructure development strategy in Afghanistan, and the road connect to some of the major regional trade corridors through Tajikistan and Pakistan.
Impact Increased domestic and international trade and personal travel.
Outcome Progress Toward Outcome
Higher level of mobility and increase in freight volumes and passenger transport services; and increased reliability and level of service on section of regional road network in northern Afghanistan. --
Outputs and Timeframe Status of Implementation Progress (Outputs, Activities and Issues)
1. Construction of part of the last missing link of the regional Ring Road
2. Emergency and ancillary works on Andkhoy-Qaisar road completed
3. Roads maintained according to pre-established performance criteria
4. Management information system (MIS) installed at MPW
Procurement of civil works services is ongoing under Grant 0244.
Under a change in scope the emergency and ancilliary civil works in Packages 1 and 2 were substantially completed in June 2010.
The maintenance component will be cancelled.
The MIS project component will be cancelled.
Geographical Location North Western Afghanistan
Safeguard Categories Safeguard Categories explained (Launches new browser window)
  Environment B
  Resettlement B
  Indigenous People C
Summary of Environmental and Social Issues No major environmental issues. SEIA prepared and posted. EMP will be prepared by the contractor during the design phase and will be reviewed by ADB.
Responsible ADB Officer Balabhaskara Reddy Bathula
David Hill
Responsible ADB Department Central and West Asia Department
Responsible ADB Division Transport and Communications Division, CWRD
Executing Agencies Ministry of Public Works
  Abdul Qudus Hamidi
  Minister
  Ministry of Public Works, Kabul
Timetable
Concept Clearance 02 May 2007
Fact-finding 07 May 2007 to 20 May 2007
Approval 28 Sep 2007