| TA Name | Songhua River Basin Water Quality and Pollution Control Management | ||||
| Country | China,People'sRep.of | ||||
| TA Number | 4061 | ||||
| Project Number | 33177- 03 | ||||
| Fund Source/Amount[Closed] |
|
||||
| Thematic Classification |
Environmental Sustainability
|
||||
| Summary of Environmental and Social Issues | Please see description | |
| Consultations Planned or Carried Out | The TA work was conducted through close consultations with all stakeholders from central and local governments, academia and NGOs. | |
| Responsible ADB Officer |
Sergei Popov |
|
| Responsible ADB Department |
East Asia Department |
|
| Responsible ADB Division |
Urban and Social Sectors Division, EARD |
|
| Executing Agencies |
State Environment Protection Administration Mr. Zhang Qingfeng, Deputy Division Director Foreign Economic Cooperation Office 115 Xizhimen Nanxiaojie, Beijing 100035, China zhangqf@svr1-pek.unep.net |
|
| Timetable | ||
| Fact-finding | 18 Sep 2002 | |
| Approval | 19 Dec 2002 | |
| Financing Plan / TA Utilization | |||||
| ADB | Others | Gov | Total | Approved Amount | Revised Amount |
| $1,000,000.00 | $0.00 | $3,000,000.00 | $4,000,000.00 | $1,000,000.00 | $988,793.31 |
| Total Commitment | Uncommited Balance | Total Disbursement | Undisbursed Balance |
| $988,793.31 | $0.00 | $988,793.31 | $0.00 |
|