Rural Basic Education Project :  Uzbekistan, Rep. of :Go to Project Summary

Rural Basic Education Project :  Uzbekistan, Rep. of

Timetable  |  Financing Plan and Loan Utilization  |  Project Outcome  |  Implementation Progress  |  Status of Covenants

Loan Name Rural Basic Education Project
Country Uzbekistan, Rep. of
Loan Number 2380
Project Number 40049- 01
Fund Source/Amount[Approved]
Asian Development Fund US$30.00  million
Thematic Classification Gender Equity
Social Development
Capacity Development
Project Outcome
Description of Outcome More equitable access to, and improved quality and relevance of, basic education in rural areas in three project oblasts.
Implementation Progress
Description of Project Outputs Component 1 - Schools in rural areas upgraded
Component 2 In-service training
for teachers
- three project oblasts
improved
Component 3 - Community
participation in rural
schools is
strengthened
Status of Implementation Progress (Outputs, Activities and Issues) Project Steering Committee is established by Presidential decree #803 on February 28, 2008.
Project Implementation Unit for RBEP is fully staffed. Office facilities for PIU have been provided by MOPE. The PIU office has been fully furnished and equipped and is being utilized.


Upgrading Rural Schools:
School selection procedures have been carried out together with Selection committees, which were established in project provinces.
At the beginning of the year by orders #14 and #35 of the MOPE 438 rural schools have been selected for participation in the RBEP.
Bidding documents for procurement of lab equipment, lab furniture, class furniture have been prepared and sent to ADB for review.
List of literature and teaching aids to be provided by the project have also been identified by the Committee (established by the order of MOPE). At present the PIU staff is working on developing specifications for them.

Teacher Development:
Recruitment of consulting firm based on QCBS procedures has been posted on ADB CSRN website on November 17, 2008. In total 11 EOIs were been received until the final deadline. CSC meeting has been held and the shortlist consisting of 6 companies was approved on 17th February 2009. RFPs have been sent to shortlisted firms on March 17, 2009.


Community Participation
Recruitment of 1 international and 1 national consultant for implementation of Component #3 of the project is also under way. The CSC conducted and approved evaluations of individual consultants and the results have also been approved by ADB.
At present the EA and the PIU are working on singing a contract with the highest ranked candidates. Fielding of consultants is expected to take place in April/May 2009.


By category as follows:

Bidding documents for equipment and furniture to be supplied to rural schools under the project have been developed by PIU and are in the process of coordination and approval;
Recruitment of consulting services for component 2 of the project has been initiated, and fielding of the Senior international consultant is envisaged in November 2009. Recruitment of international and local consultants for component 3 will be finalized in March/April 2009 and both consultants are expected to be fielded in April/May 2009;
Learning materials under the project will be developed by international and local consultants towards the end of 2009 and first half of 2010;
For the purposes of publicity campaign, a local media firm is expected to be engaged in June-July of 2009;
Linkage to Country/Regional Strategy In accordance with the Government's development strategy, the Project is included in the country strategy and program (CSP) update 2006-2008.
Geographical Location Uzbekistan
Safeguard Categories Safeguard Categories explained (Launches new browser window)
  Environment C
  Resettlement B/C
  Indigenous People B
Responsible ADB Officer Asadullah Sumbal
Responsible ADB Department Central and West Asia Department
Responsible ADB Division Financial Sector, Public Management and Trade Division, CWRD
Executing Agencies Ministry of Public Education
  Mr. R. Aklidinov
  First Deputy Minister
Timetable
Concept Clearance 27 Oct 2005
Fact-finding 01 May 2007 to 28 May 2007
Board Approval 06 Dec 2007
Last Review Mission 22 Oct 2008
CLOSING
Loan No. Approval Signing Effectivity Original Revised Actual
2380-UZB(SF) 06 Dec 07 10 Jun 08 30 Sep 08 30 Jun 12 - -

Financing Plan Top Loan Utilization
  TOTAL ( Amount in US$ million)
PROJECT COST 43.000
ADB 30.000
Government 13.000
Date ADB OTHERS Net Percentage
Cumulative Contract Awards
31 Oct 09 0.536 0.000 2%
Cumulative Disbursements
31 Oct 09 0.151 0.000 0%
Top Status of Covenants
Category Sector Environmental Social Financial Economic Others Overall
Rating Highly Satisfactory Satisfactory Not Yet Due Satisfactory Satisfactory Satisfactory