Asian Development Bank - Fighting Poverty in Asia and the Pacific
What's New  |   e-Notification  |   Sitemap  |   Contact Us  |   Help

Projects

Home : Projects : Project Information Documents


Liaoning Environment Improvement Project :  China,People'sRep.of :Go to Project Summary

Liaoning Environment Improvement Project :  China,People'sRep.of

Timetable  |  Financing Plan and Loan Utilization  |  Project Outcome  |  Implementation Progress  |  Status of Covenants

Loan Name Liaoning Environment Improvement Project
Country China,People'sRep.of
Loan Number 2112
Project Number 36362- 01
Fund Source/Amount[Closed]
Ordinary Capital Resources US$70.00  million
Description The long-term goal of the Project is to support environmental improvement in Liaoning Province. The main objectives of the Project are: (i) improvement in efficiency and reliability of gas and central heating supply and closure of small coal-fired boilers, and (ii) CMM and CBM production and commercial utilization. The Project includes the following components: (i) Part A: CBM/CMM development; (ii) Part B: gas distribution improvement; (iii) Part C: city central heating supply, and (iv) Part D: institutional reforms and corporate governance improvement.
Project Rationale Part A of the Project is designed to utilize CBM/CMM to reduce GHG emissions and improve coalmine safety. The gas distribution systems owned and operated by Fushun Gas Company and Benxi Gas Company are inefficient with high distribution losses. They are also dangerous hazardous as the pipelines are aged and often cause explosion. To address these problems, Part B of the Project will rehabilitate Fushun and Benxi Gas Company's gas distribution systems to reduce distribution line losses, improve operation safety and supply gas to additional households to help reduce coal consumption. Part C of the Project will improve environmental quality by building efficient and large boilers to facilitate closing the 412 existing small coal-fired boilers. Part D of the Project includes three areas: (a) restructuring of the project implementing agencies (PIAs), (b) institutional strengthening and training, and (c) a study to assist the PIAs to implement the central heating tariff reforms and assess the options for the private sector participation. The objectives for ADB's operations in the PRC include: (i) promote equitable and inclusive growth; (ii) make markets work better; (iii) foster regional cooperation; and (iv) promote environmental sustainability, which includes encouraging the use of clean production technologies and renewable energy etc. Methane, part of natural coal composition, is released into the atmosphere from coal mine operations. It is estimated that the coal mines in Liaoning released about 1.2 billion cubic meters of methane into the atmosphere in 2003, a figure expected to reach 2.0 billion cubic meters by 2010. Methane, when released into the atmosphere, is about 21 times more potent as a greenhouse gas than carbon dioxide. In addition, coal mine safety is a major concern in the PRC, which reported deaths of 6,900 miners in 2002. Overall, the Project is consistent with ADB's operational strategy in the PRC and was listed in ADB's Country Strategy and Program (2004-2006). The Project will support the government of Liaoning province (GLP) in aiming to improve environmental quality and coal mine safety, and to ensure that the poor have sufficient gas and central heating.
Impact Environmental improvement in Liaoning Province.
Project Outcome
Outcome Progress Toward Outcome
Improvement in efficiency and reliability of gas and central heating supply Progress has been made toward outcome.
Implementation Progress
Outputs Status of Implementation Progress (Outputs, Activities and Issues)
1. Increased CMM/CBM production and utilization
2. Rehabilitated and expanded gas distribution systems
5. Implemented assistance programs for the poor households
3. Augmented central heating systems to facilitate closure of small inefficient coal-fired boilers
4. Developed institutional and financial tariff reform action plan, and privatization plan
Completed.
Completed.
Completed.
Completed.
Completed.
Geographical Location Liaoning Province (Benxi, Fuxin, Liaoyang, and Yingkou)
Safeguard Categories Safeguard Categories explained (Launches new browser window)
  Environment B
  Resettlement B
  Indigenous People B
Summary of Environmental and Social Issues
Environmental Aspects to be determined
Stakeholder Participation and Consultation
During Project Design Consultations with stakeholders, including various levels governments, implementing agencies, and beneficiaries were undertaken.
During Project Implementation Consultations with stakeholders, including various levels governments, implementing agencies, and beneficiaries were undertaken.
Responsible ADB Officer Xinjian Liu
Responsible ADB Department East Asia Department
Responsible ADB Division Energy Division, EARD
Executing Agencies Government of Liaoning Province
  Mr. Teng Da
  Director, LDRC Foreign Fund Utilization Project Office
  No. 13 Shisiweilu, Heping District, Shenyang 110003
  n.a.
Timetable
Concept Clearance 07 Mar 2004
Fact-finding 30 Oct 2003 to 21 Nov 2003
Appraisal 12 Apr 2004 to 27 Apr 2004
Board Approval 25 Nov 2004
CLOSING
Loan No. Approval Signing Effectivity Original Revised Actual
2112-PRC 25 Nov 04 26 May 05 16 Nov 05 30 Sep 09 30 Sep 11 -

Financing Plan Top Loan Utilization
  TOTAL ( Amount in US$ million)
Project Cost 56.70
ADB 56.70
Counterpart 0.00
Cofinancing 0.00
Date ADB OTHERS Net Percentage
Cumulative Contract Awards
08 Feb 2012 52.421 93%
Cumulative Disbursements
08 Feb 2012 56.431 100%
Top Status of Covenants
Category Sector Social Financial Economic Others Safe
Rating Satisfactory Satisfactory Satisfactory Satisfactory
© 2008 Asian Development Bank

Privacy | Terms of Use
  Top of page