TA Name Urban Water Supply and Sanitation Project
Country Philippines
TA Number 7683
Project Number 42363- 01
Source of Funding/Amount[Approved]
A.T.F. - French T.A. Grant US$2.00  million
Thematic Classification Economic growth
Social Development
Capacity Development
Outcome Progress Toward Outcome
Agreed loan project suitable for ADB to consider financing. --
Outputs and Timeframe Status of Implementation Progress (Outputs, Activities and Issues)
1. Updated water demand forecast, current supply capacity, and MCWD strategic water sourcing plan
2. Agreed upon ADB fund channeling arrangement
3. Detailed assessment of NRW level and finalized water
4. Distribution expansion plan developed
5. Asset management system development plan completed
6. Feasibility study and preliminary design of Kotkot/Lusaran dam system formulated
7. Corporate development and capacity building program formulated
8. Assessment of potential private sector involvement (NRW reduction, source development) completed
9. Investment program for non-revenue water reduction, network improvement and expansion, and water source development completed
Responsible ADB Officer Paulus B. van Klaveren
Responsible ADB Department Southeast Asia Department
Responsible ADB Division Urban Development and Water Division, SERD
Timetable
Approval 26 Nov 2010
Financing Plan / TA Utilization Top TA Amount
ADB Others Gov Total Approved Amount Revised Amount
$0.00 $0.00 $0.00 $0.00 $2,000,000.00 $0.00
 Total Commitment Uncommited Balance Total Disbursement Undisbursed Balance
$1,684,101.00 $315,899.00 $1,106,843.95 $893,156.05