Preparing the Road Network Development Project :  Timor-Leste :Go to Project Summary

Preparing the Road Network Development Project :  Timor-Leste

Timetable  |  Financing Plan and TA Utilization


TA Name Preparing the Road Network Development Project
Country Timor-Leste
TA Number 7100
Project Number 38618- 02
Thematic Classification
Economic growth
Gender Equity
Capacity Development
Description This PPTA will evaluate the suitability and prepare a National Road Improvement Program, a road maintenance program adopting sector-wide approach (SWAp), and a program for participation of communities in the development of rural roads.
Linkage to Country/Regional Strategy TA is included in the country strategy and program update (2006¿2008) and the country operations business plan (2008¿2010) for Timor-Leste
Impact The TA will contribute to the Government's objective of an improved and sustainable road network in Timor-Leste. The TA will help the Government in reducing the cost of transportation and improving the road network for economic development and social integration. The TA will also assist MOI in preparing its national development plan for road infrastructure and identifying institutional and policy reforms needed to improve sector performance.
Geographical Location Timor-Leste
Safeguard Categories Safeguard Categories explained (Launches new browser window)
  Environment B
  Resettlement B
  Indigenous People C
Stakeholder Communication, Participation and Consultation
During Project Design Extensive consultation was done with the Government and other donors during the implementation of previous projects. More consultation will be conducted. In addition, the lessons learned under Emergency Infrastructure Rehabilitation Projects, Phases 1 and 2, and the ongoing Road Sector Improvement Project will be considered in the preparation of proposed RSIP II.
Responsible ADB Officer Chen Chen
Responsible ADB Department Pacific Department
Responsible ADB Division Pacific Operations Division
Executing Agencies Ministry of Infrastructure
Timetable
Concept Clearance 07 Apr 2008
Fact-finding 08 Apr 2008 to 17 Apr 2008
Approval 23 Jul 2008
Financing Plan / TA Utilization Top TA Amount
ADB Others Gov Total Approved Amount Revised Amount
$800,000.00 $200,000.00 $800,000.00 $757,899.11
 Total Commitment Uncommited Balance Total Disbursement Undisbursed Balance
$757,899.11 $42,100.89 $757,899.11 $42,100.89
© 2008 Asian Development Bank

Privacy | Terms of Use
  Top of page