| TA Name | Preparing the Road Network Development Project | |||||||||||||||||||||||||||
| Country | Timor-Leste | |||||||||||||||||||||||||||
| TA Number | 7100 | |||||||||||||||||||||||||||
| Project Number | 38618- 02 | |||||||||||||||||||||||||||
| Thematic Classification |
Economic growth Gender Equity Capacity Development |
|||||||||||||||||||||||||||
| Description | This PPTA will evaluate the suitability and prepare a National Road Improvement Program, a road maintenance program adopting sector-wide approach (SWAp), and a program for participation of communities in the development of rural roads. | |||||||||||||||||||||||||||
| Linkage to Country/Regional Strategy | TA is included in the country strategy and program update (2006¿2008) and the country operations business plan (2008¿2010) for Timor-Leste | |||||||||||||||||||||||||||
| Impact | The TA will contribute to the Government's objective of an improved and sustainable road network in Timor-Leste. The TA will help the Government in reducing the cost of transportation and improving the road network for economic development and social integration. The TA will also assist MOI in preparing its national development plan for road infrastructure and identifying institutional and policy reforms needed to improve sector performance. | |||||||||||||||||||||||||||
|
|
||||||||||||||||||||||||||||
| Geographical Location | Timor-Leste | |||||||||||||||||||||||||||
| Safeguard Categories
|
||||||||||||||||||||||||||||
| Environment | B | |||||||||||||||||||||||||||
| Resettlement | B | |||||||||||||||||||||||||||
| Indigenous People | C | |||||||||||||||||||||||||||
| Stakeholder Communication, Participation and Consultation | ||||||||||||||||||||||||||||
| During Project Design | Extensive consultation was done with the Government and other donors during the implementation of previous projects. More consultation will be conducted. In addition, the lessons learned under Emergency Infrastructure Rehabilitation Projects, Phases 1 and 2, and the ongoing Road Sector Improvement Project will be considered in the preparation of proposed RSIP II. | |||||||||||||||||||||||||||
| Responsible ADB Officer |
Chen Chen |
|||||||||||||||||||||||||||
| Responsible ADB Department |
Pacific Department |
|||||||||||||||||||||||||||
| Responsible ADB Division |
Pacific Operations Division |
|||||||||||||||||||||||||||
| Executing Agencies |
Ministry of Infrastructure |
|||||||||||||||||||||||||||
| Timetable | ||||||||||||||||||||||||||||
| Concept Clearance | 07 Apr 2008 | |||||||||||||||||||||||||||
| Fact-finding | 08 Apr 2008 to 17 Apr 2008 | |||||||||||||||||||||||||||
| Approval | 23 Jul 2008 | |||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||
|