1. Component A: Community Mobilization, Capacity Development, and Training - in progress
- Quantity of training course: 58 courses/10 wards/66 hamlets.
- Quantity of training title: 6 titles (Community promotion skill, Grassroots democracy ordinance, Project cycle management with participation of community, several methods of quick review with attention of... Investment procedural variation, Accounting record management). Of which there are 02 training course conducted by Asian Institution of Technology - AITVN at the end of 12/2010 on skill and method of promotion/administration. Morever, AF-Colenco consultant held on conference on project implementation review at the end of 6/2011.
- There were total of 2,437 paticipations in training courses (in which: commune/ward CMCs: 321 lpaticipations; Hamlet CMCs 2.116 paticipations). Average portion of female participant: 30,7%.
2. Component B: Community Infrastructure Grants - in progress
- Nam Ngan ward: Comprises 08 sub-projects, commenced in 12/2010, finalized construction, handed over and put in operation in 3/2011, conducted Payment and reimbursement.
- Dong Hai commune: Comprises 05 sub-projects, commenced in 12/2010, finalized construction, handed over and put in operation in 3/2011, conducted Payment and reimbursement.
- Dong C¿uong commune: Comprises 05 sub-projects, commenced in 12/2010, finalized construction, handed over and put in operation in 3/2011, conducted Payment and reimbursement.
- Quang Thanh commune (08 sub-projects),Quang Hu¿ng commune (08 sub-projects), Xua Lam commune (08 sub-projects), commenced in 5/2011 scheduled to finish in 10/2011. Up to now, the majority of subprojects have finished construction for handing over and puting in operation. It estimates to be 85-90%
- Thieu Trung commune (07 sub-projects). commenced in 8/2011 scheduled to finish in 11/2011. Up to now, the majority of subprojects have finished construction for handing over and puting in operation. It estimates to be 60-65%.
+ Dong Tho ward (08 sub-projects). commenced in 8/2011 scheduled to finish in 11/2011. Up to now, the majority of subprojects have finished construction for handing over and puting in operation. It estimates to be 60-65%.
+ Ham Rong ward (07 sub-projects), Quang Thang commune (08 sub-projects) have finished procurement, expected to commence in 10/2011 and finish in 12/2011.
3. Component C: Project Management, Monitoring and Audit - in progress
- Independent Auditor mobilized, auditing report just submitted to ADB in Oct
- Mid-term ealuation specialist recruited, will join the ADB midterm review, the contract will expire in Dec 2011
|