Shaanxi Qinling Biodiversity Conservation and Demonstration Project :  China,People'sRep.of :Go to Project Summary

Shaanxi Qinling Biodiversity Conservation and Demonstration Project :  China,People'sRep.of

Timetable  |  Financing Plan and Loan Utilization

Grant Name Shaanxi Qinling Biodiversity Conservation and Demonstration Project
Country China,People'sRep.of
Grant Number 169
Project Number 39321- 03
Fund Source/Amount[Approved]
Global Environment Facility US$4.27  million
Geographical Location Qinling Mountains are located 40 km south of Xian
Procurement
  Consulting Services Consultants will be recruited in line with ADB's Guidelines on the Use of Consultants (2007, as amended from time to time). The Project will provide 84 person-months of consulting services, comprising 15 person-months of international experts and 69 person-months of national experts. These services will be procured in two packages. For package A, which will be financed under the GEF grant, QNBG's SARC division will select and engage six individual consultants for 1 month each-one international and one national expert for each of the giant panda, crested ibis, and golden monkey habitats and plans for effective conservation. For package B, which will also be financed under the GEF grant, the PMO will select and engage a consulting firm using the quality- and cost-based selection method (80:20) and the full technical proposal procedures. The consulting firm will provide expertise in biodiversity conservation, species recovery management, ecotourism planning, village development planning, animal exposition and breeding, wildlife veterinary services, species recovery and survey, conservation forestry, and geographic information systems.
Responsible ADB Officer Raymond Z. H. Renfro
Responsible ADB Department East Asia Department
Responsible ADB Division Agriculture, Environment, and Natural Resources Div, EARD
Executing Agencies Shaanxi Provincial Government
  ABO@SEIN.SXGB.COM.CN
Timetable
Concept Clearance 10 Aug 2007
Board Approval 22 Oct 2009
CLOSING
Grant No. Approval Signing Effectivity Original Revised Actual
0169 22 Oct 09 31 Oct 15

Financing Plan Top Grant Utilization
  TOTAL ( Amount in US$ million)
PROJECT COST ($ million) 5.000
GEF 5.0 5.000
Date ADB OTHERS Net Percentage
Cumulative Contract Awards
31 Oct 09 0.000 0.000 0%
Cumulative Disbursements
31 Oct 09 0.000 0.000 0%