| Loan Name | CAM: GMS Rehabilitation of the Railway in Cambodia (Supplementary) | |||
| Country | Regional | |||
| Project Number | 37269- 02 | |||
| Fund Source/Amount[Proposed] |
|
|||
| Thematic Classification |
Economic growth
|
|||
| Impact | Domestic and regional trade movement via the railway increases; and the railway system is sustainable. | |||
| Outcome | An improved railway system is operational. | |||
| Outputs |
1. Existing railway line rehabilitated and partially upgraded, enabling safe operations at a mainline speed of at least 50 km/hr.
2. Railway link to Thailand is reconstructed. 3. Rail links to Sihanoukville port and the port in Phnom Penh rehabilitated and extended. 4. Feight facilities in Samrong and Phnom Penh constructed. 5. Affected households living within the railway ROW and stations satisfactorily compensated and assisted. 6. Railway agency is operational. |
|||
| Safeguard Categories
|
||||
| Environment | B | |||
| Resettlement | A | |||
| Indigenous People | C | |||
| Procurement | ||||
| Consulting Services | The consultants will be selected by the Government in accordance with ADB's Guidelines on the Use of Consulting Services, using the quality and cost based selection procedure and simplied technical proposal. | |||
| Civil Works/Goods |
The works will be carried out under the international competitive bidding procedures of ADB's Guidulines on Procurement. There will be two contracts for the Samrong facilitiy, one for the earthworks and the other for the buildings, equipment and services, trackwork, and roadworks.
There will also be a supply contract for the provision of rail for the Samrong facility and replacement of sections of rail on the northern line. |
|||
| Responsible ADB Officer |
Peter Broch |
|||
| Responsible ADB Department |
Southeast Asia Department |
|||
| Responsible ADB Division |
Transport and Urban Development Division, SERD |
|||
| Executing Agencies |
Ministry of Public Works and Transport |
|||
| Timetable | ||||
| Concept Clearance | 13 May 2009 | |||
| Fact-finding | 29 Jul 2009 to 07 Aug 2009 | |||
| Appraisal | 23 Sep 2009 to 02 Oct 2009 | |||
| Board Approval | 15 Dec 2009 | |||
|